Suncook River Stabilization


 

 

2011 Suncook River stabilization study field meetingThe Suncook River in Epsom, NH abruptly changed course in 2006 as a result of spring storms and flooding. This avulsion caused the abandonment of two river channels west of Bear Island and created a new, shorter, and steeper channel to the east. The Suncook River is continuing to adjust to its shorter channel length by migrating laterally (moving from side to side) and incising (cutting down deeper into the river bed).  The lateral migration of the Suncook River to the east combined with the incision has triggered similar responses in both the Little Suncook River and Leighton Brook as they continue to adjust to the changes on the Suncook River. 
 
One of the major concerns stemming from the avulsion is upstream erosion in the vicinity of the Route 4 Bridge and the stream crossings under Black Hall Road in Epsom. When the Suncook River changed course, the slope of the river became steeper at the avulsion site and large amounts of loose sediment were washed downstream. As a result, another form of erosion called headcutting began to occur and gradually move upstream from the avulsion site. This is a natural process that happens as a river attempts to restore its equilibrium relative to slope, length, erosion rates and sediment transport. However, if left unchecked, such headcutting may introduce increased vulnerability to important infrastructure such as the Route 4 Bridge east of the Epsom traffic circle and the stream crossings under Black Hall Road.
 
DES Contractor, Inter-Fluve, surveying the Suncook River in 2011The New Hampshire Department of Environmental Services (NHDES)is coordinating a multi-agency led project to develop designs and permits for the protection of critical infrastructure located on the Suncook River, Leighton Brook and the Little Suncook River.  This project will prepare the necessary work scope and budget to proceed with construction.
 
Fieldwork for the geophysical survey and geomorphic assessment began in 2011 and will conclude during the spring of 2012. NHDES anticipates that the construction of stabilization measures on the Suncook River and Leighton Brook will occur in 2013. Design and permitting for this project were made possible through a grant from the Federal Emergency Management Agency and the New Hampshire Department of Safety.  A significant percentage of funding for construction activities was secured through a special capital appropriation made by the New Hampshire Legislature in 2011.

 

 

Topographic Survey Points taken in Epsom in 2011

Resources:

 

Technical Memos:

 

Inter-Fluve Technical Memo: Rough Cost Estimate for Single Valley-Spanning Rock Grade Control Structure, January 2012

 

Inter-Fluve Technical Memo: Basis of Design 30% Complete, December 2011

 

Inter-Fluve 30% Complete Design Sheets, December 2011

 

 

Click image above  to view 2011 topographic

survey points  for the Suncook River

stabilization study.

 

NHDES Update on the Suncook River Design and Permitting Project, July 2011

 

Analysis of the Transport of Sediment by the Suncook River in Epsom, Pembroke, and Allenstown, New Hampshire, after the May 2006 Flood, November 2011

 

Request for Proposals and Qualifications: Geomorphology-based Restoration Design and Permitting for the Suncook River in Epsom, NH, 2009 

 

Website maintained and hosted by CNHRPC ~ Contact Website Administrator ~ Joomla 1.6 Template by sinci